July-August 2009

Medical Power Practices

Case studies in standby emergency power

Article Tools

Create a Link to this Article

Photo: @iStockphoto.com/Maksymka

By Lori Lovely

1 Comments


Running two feeders across the street to the double-ended emergency unit sub-station required excavation. But that wasn’t the only aspect that necessitated precise timing. When 26 transfer switches were swapped from the old to the new generators, they were moved over a couple weekends in December 2006. “It was a big feat!” exclaims Ross. “Through much planning and preparation before the weekend shutdowns, the team reconnected all transfer switches, tested all control signals, and put them back in operation without a problem. The patients and staff experienced no disruptions.”

In fact, he says, it was not a true shutdown because there was no loss of power.

Passing the Test
Buckner told Caterpillar that the University did “extensive testing of each generator and each transfer switch, because we couldn’t have a situation where the hospital wasn’t covered. In fact, we conducted a continuous 36-hour run test of all four generators synchronized to the board after each of the generators was extensively tested individually, so that we could simulate an extended power curtailment from our local utility.” They also conducted four different shutdowns to individually test “each and every start signal and each load shed from the 31 transfer switches associated with the power plant.”

Confidence is running high, thanks to successful test results and a system that’s simple to operate, test, and maintain. “Everything is going according to plan,” summarizes Ross. “The first phase was to get it in place and get the loads transferred. Everyone’s happy: It’s very quiet and the new generators are dedicated for patients.”

Carolinas Hospital—Growth and Compliance
VUMC isn’t the only medical facility trying to keep up with its own growth. Carolinas Hospital System (CHS) in Florence, SC, moved into a multi-million dollar medical campus in 1998, but continued to experience growth and increased power loads. Serving patients in a nine-county area with state-of-the-art equipment, CHS provides acute care, cancer treatment, cardiac care, emergency/trauma services, maternity care, and an array of specialized rehabilitation programs.

Photo: Eaton Corporation
The Blade UPS server room is an integral part of Non-Destructive Testing.
The need to meet The Commission’s full power redundancy and standby power requirements and Health Insurance Portability and Accountability Act (HIPAA) requirements, as well as accommodate increasing information technology (IT) demands and achieve greater reliability and continuous availability of its IT systems, meant that it was time to bolster its power protection efforts in two critical areas: its patient health information servers and its primary distribution cabinet.

“Our initial UPS implementation was not designed to accommodate the entire data center,” explains Ray Graham, IT consultant for Carolinas Hospital System. “Power protection is a vital part in maintaining our technology infrastructure.”

Thus, they sought a solution that would address their immediate data center requirements as well as future expansion plans.

Although code requirements for essential systems and emergency backup power for critical and life safety are clear, IT systems requirements are less so. However, with the typical commercial customer experiencing four to 15 outages per year, it was obvious to Graham that CHS’ IT infrastructure was susceptible to daily power quality issues such as surges, sags, load fluctuations, and other power interferences. “We view technology as an asset to facilitate even better care for hospital patients,”  he says. “In a hospital environment, downtime must be avoided as critical equipment and patient information is needed around the clock.”

A proactive plan for power protection and management strategies to protect IT systems, diagnostic imaging equipment, clinical labs, and monitoring support systems against a full range of problems was implemented.

Powering Up
The hospital’s data center serves 1,800 users and houses 50 servers, generating and storing large volumes of critical patient health care information. When CHS relocated in 1998, its uninterruptible power system was already approaching capacity. In 2005, the data center added two additional units to power its servers, but it wasn’t long before those Powerware 9125s were also near capacity.

To ensure protection for its data, hospital administrators hired Jones Engineering, an engineering contractor based in South Carolina, to determine the appropriate specifications needed. They identified several criteria, such as total system scalability, battery runtime, and redundancy requirements, before ultimately recommending Eaton’s Powerware BladeUPS solution.

The deciding factor, Graham states, was the system’s modular design and built-in bypass capability. “With a modular system, there are no downtime requirements, and when additional capacity is needed, you simply plug in another module,” he adds.

Success with previous Powerware products confirmed their choice. Eaton’s Powerware BladeUPS is the industry’s most energy-efficient, rack-based, three-phase system, specifically designed and optimized for today’s high-density computing environments.

Another reason CHS opted for the Powerware system relates to additional features not available with other UPS systems. CHS liked the integral network-monitoring feature, which allows e-mail notifications about power events to be sent in advance of cutting servers over to backup power. The UPS is programmed to distribute pager and e-mail notification for both critical and major power events and allow the IT staff to examine the load to determine how many more devices can be added before reaching capacity.

Photo: Eaton Corporation
Remote visual inspection is possible with Data Module installation.
Plugged in
Two weeks from placing the order in January 2007, CHS installed two 12-kW Powerware BladeUPS modules, with the capability to store five modules in a single 19-inch rack, for a total of 60-kW. Because the two modules are in redundant mode, staff can perform full maintenance on any module without interruption of conditioned power to their IT equipment.

Once the Powerware BladeUPS system was installed, staff began migrating its critical servers. Additionally, eight servers containing primary patient information systems were also transferred. Plans are in place to remove the old UPS and power the entire data center with the Powerware BladeUPS. The two Powerware 9125 units are also scheduled to be moved to the hospital’s main distribution closet, to provide power protection for core networking equipment that supports hospital connectivity to all remote sites. “We are now using UPS systems in our two most critical areas—patient health information servers and our primary distribution closet,” reveals Graham. “This strategy is essential, because the Powerware BladeUPS now bridges the gap between loss of utility power and locally generated power. We have complete confidence that we will not experience power problems that harm our computers, data, or affect patient care.”

Eventually, everything in its data center will be transferred to the Powerware BladeUPS, including clinical, radiology, and facility applications—including accounting and payroll applications—as well as all infrastructure systems, networking components in the data center, and current domain support systems. An additional six servers will be added to support that transition and implementation of an entirely new health information systems application.

Advertisement

Carolinas Hospital depends on the UPS to maintain its critical healthcare systems. “Downtime procedures are a last resort, because we cannot prolong the amount of time required to provide care and services to patients,” explains Graham.

Downtime also increases costs, while simultaneously decreasing patient satisfaction. “Anything we can do to prevent that is a plus.”

Author's Bio: Lori Lovely is a freelance writer based in Indianapolis, IN.

What Do You Think?

Post a Comment

jobigger

July 2nd, 2009 7:47 AM PT

I have been a reader/subscriber of Distributed Energy since Issue No. 1 and look forward to each issue. That said, I found the author's descriptions in "Medical Power Practices" of the equipment and systems for Vanderbilt University's Medical Center emergency power system to be very confusing. A large portion of the word descriptions in the article could have been replaced by simplified one-line diagrams of the hospital campus systems, for instance. And what cost and performance information that was provided was sprinkled throughout the article; a concise summary is much more valuable to the reader (see, for example, Table 1 on page 20 of this issue). The Caterpiller units are impressive but one or two of the photos could have been replaced with other graphics that would increase the reader's understanding of the overall system's operation and benefits. Connecting together various emergency and alternative electric generating systems to create high-efficiency, -reliability, or -security networks on a university campus, medical complex, or industry development is being recognized as an opportunity for significant savings of energy and funds. Clarity is critical to describing these projects. For a comparison, an article appeared in the April 2009, issue of POWER magazine (page 22) describing a similar project to increase reliability of the Illinois Institute of Technology campus in Chicago, Illinois.

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Distributed Energy Email Updates!

Get weekly news and updates through our Distributed Energy email newsletter!